titleHow is OEE calculated?

Shoplogix follows the official OEE calculation standard. However, it may vary from customer to customer. Depending on the view and timeframe, the values are edited and filtered for the particular display.

OEE = Availability * Performance * Quality

Check our How OEE is calculated? article for step-by-step math, examples and some other details.

Expand
titleHow do I enter a downtime reason?

You can add a downtime reason from many views. In this example, we are using the Hourly View.

  1. Open the Whiteboard

  2. Select the Hourly View for the machine you want to add a downtime reason to

  3. Find the hour when the downtime occurred

  4. Click on the grey box that shows the downtime as shown below

  5. Select a downtime reason from the dropdown list, select time duration, and click save.

...

Expand
titleHow do I return to the home page on the Whiteboar?

The fastest way to return to the homepage from any view on the whiteboard is just to click on the Shoplogix logo on the top left corner of the whiteboard.

Image RemovedImage Added
Expand
titleHow do I look at previous shift history?

To navigate shift history, simply use the navigation arrows located at the top right and left corners of the screen. Keep track of the shift name and date easily from the top center section of the screen.

...

Expand
titleCan I overlay the layout view on our own layout?

This feature does not exist in the current version of our software. However, it is under consideration for a more robust version of this feature. However, there is no expected timeline for the approved development.

Expand
titleHow is OEE calculated?

Shoplgix follows the official OEE calculation standard. However, it may vary from customer to customer. Depending on the view and timeframe, the values are edited and filtered for the particular display.

OEE = Availability * Performance * Quality

Expand
titleHow is Cycle TIme Calculated?

Cycle time is the time calculated between 2 produced parts i.e. the time between the PLC signals for produced parts, for more precise values.

...

Expand
titleHow can I change a downtime reason?

To change downtime reason:

  1. You need to open a view that supports that on the whiteboard (e.g. Hourly view, Chrono view)

  2. Select the downtime reason you are changing from

  3. Select the downtime reason you want to change to

  4. Click  Save.

Expand
titleHow are the metrics on the Whiteboard calculated?

Here is a list of the most popular metrics on the Whiteboard:

  • OEE = Availability * Performance * Quality

    • Availability = Uptime / Planned Productive Time

    • Performance = ( Number of parts produced) / (Machine rate * Uptime)

    • Quality = [(Number of parts produced) - (Number of parts rejected)] / (Number of parts produced)

  • OEE = Availability * Performance * Quality Ratio

  • OEE = Good Production (pcs) / ( Expected speed (parts/hr) * Scheduled Time (hr) )

If you’re interested in learning more about metrics on the Whiteboard and checking some examples, you can check this article.