The Meeting view displays each shift within the chosen time period, machine chronological report, production count bars, and different gauges. It defaults to a 24 hour period. This view is very similar to Machine Chrono.
Figure 5-33: Meeting View
From this view, you can navigate to shifthours by clicking on the Title and Time area.
Figure 5-34: Hourly view from clicking Meeting view title
The Job Bar Color, Job Identifier and Metrics at the top of the Machine Chrono view will change as follows:
Green is when the job has been completed.
Figure 5-35: Machine Chrono View with a Green Job Identifier
Blue is when the current job target has not been met.
Figure 5-36: Machine Chrono View with a Blue Job Identifier
Orange is when the current job target has been exceeded.
Figure 5-37: Machine Chrono View with a Orange Job Identifier
The settings for this view are the same as Machine Chrono, all the steps are described in section 5.3 of the User Guide.