Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 3 Current »

The Meeting view displays each shift within the chosen time period, machine chronological report, production count bars, and different gauges. It defaults to a 24 hour period. This view is very similar to Machine Chrono.

Figure 5-33: Meeting View

From this view, you can navigate to shifthours by clicking on the Title and Time area.

Figure 5-34: Hourly view from clicking Meeting view title

The Job Bar Color, Job Identifier and Metrics at the top of the Machine Chrono view will change as follows:

Green is when the job has been completed.

Figure 5-35: Machine Chrono View with a Green Job Identifier

Blue is when the current job target has not been met.

Figure 5-36: Machine Chrono View with a Blue Job Identifier

Orange is when the current job target has been exceeded.

Figure 5-37: Machine Chrono View with a Orange Job Identifier

The settings for this view are the same as Machine Chrono, all the steps are described in section 5.3 of the User Guide.

  • No labels